Arklow Water Supply Scheme

The Minister for the Environment, Community and Local Government has approved funding to allow Wicklow County Council to accept the tender of AECOM-Cradock JV for the Arklow Water Supply Scheme Water Treatment Plant Upgrade. This is a Design/Build/Operate Contract and PUNCH Consulting Engineers are designers for the JV. Aecom will design and operate the treatment process and John Cradock Ltd will be responsible for the design and construction of the civil and structural works.

The contract comprises the construction of a new Water Treatment Plant at Ballyduff, the equipping and commissioning of the production wells and the upgrading of the existing abstraction facility at the Goldmines River. The new plant will supply 6.1Ml/day of treated water.

Design work and construction of the scheme will commence shortly.